Project Status Report 2 - (Amber)



Core Application Code Development

The development of the code is going well. The core application code has been completed. All database inserts and updates have been tested and done. There are still alot of boundry condition tests that need to be completed they will be taken care of at a later state.

The delete and edit components of the code still need to be done but should be a much easier task as now the information can be refreshed and inserted and displayed on the html interface.

Alot of code cleanup needs to take place because certain shortcuts where taken when doing the first cut of the code, mainly to ensure that each of the concepts that were discussed worked

Looks like final V1.0 version of the code will not be ready until atleast the end of february or march depending on how things progress

Template Development

Templates are coming along good. There have been 4 base templates designed in photoshope but not yet translated into HTML. That is currently being completed.

This along with all the javascript code that comes with each of the templates also is in the process of being completed. Currently the code all works but is not in a state that would be good for future maintenance and a v1.0 release.

Some javascript needs to be cleaned up and various blocks of code rearranged to ensure that future maintenance is manageable. All in all however the code all works and all POC's (proof of concepts) have been completed.

Mobile Device Webapp

We are still in the processes of setting up the environment for the mobile device webapp. There are still documents to read and understand, however this is not a major concern as yet as the mobile device webapp will be in version 2.0 of the software.

Summary

At the moment thats our status. Things progressing well but we have the issue with only having 24 hours in the day and a team of 3 who are also holding full time jobs. Its not easy but it sure is fun and exciting ... So why are we amber, because we had an initial launch date for end of january but that doesnt seem like it will be the case at the moment ...

.
.
.
.

Till the next entry ... Garage Datacenter CEO signing off the status report ...